Sandwich Wall Panels Installation Process

Paying-off and Sandwich Wall Panels Arrived on Site

sandwich panel installation 1
sandwich panel installation 2

Adopting high precision laser alignment instrument to eject double lines of panel thickness on axial line of panel installation location, move the panel to the settled location according to different spectifications.

Sawing Panel According to Requirement

sandwich panel installation 3
sandwich panel installation 4

Adopting hand-hold electric saw cutting the panel according to different need, make sure maximum using each panel to reduce the waste.

Sizing

sandwich panel installation 5
sandwich panel installation 6

Sizing the bump slots and even up the special BOYUEJIA panel adhesive into the bump slots and baseline of the floor.

Installation

sandwich panel installation 7
sandwich panel installation 8

Erected the painted panel with adhesive and move it to the prepared installation site, adjusting the panel to fit both of the baseline and tighten each panel to push the extra polymer mortar out of the joint crack, fixing the panel by wooden wedge.

Correction and Fixation

sandwich panel installation 9
sandwich panel installation 10

Correcting the panel position by using 2m levelness & verticality straight guide rule, adopting expansion rubber together with 6mm or 8mm steel bar to fix the panel.

Grouting and Filling Thick Liquid

sandwich panel installation 11
sandwich panel installation 12

Leave the installed and corrected panel for one day, adopting BOYUEJIA special panel adhesive to filling the joint crack. Remove wooden wedge and smooth the crack by polymer mortar.

Slotting and Wiring

sandwich panel installation 13
sandwich panel installation 14

Adopting hand-electric saw to cut the slotting for switch box or concealed line if needed, smooth the slotting by polymer mortar after installation.

Sticking Anti-Crack Tape

sandwich panel installation 15
sandwich panel installation 16

Sticking anti-crack tape in 3-5 days after grouting to prevent crack which may caused by long time expansion or contraction.

Installing Door Frame

sandwich panel installation 17
sandwich panel installation 18

Reserve holes for door and window, and fixing the holes by plywood line anchor.

Decoration

sandwich panel installation 19
sandwich panel installation 20

Sandwich wall panel do not need extra plaster for the surface, decorating the wall surface directly by tiles, wallpaper or other painting.

Sandwich Wall Panels Installation Tools

Sandwich Wall Panels Installation Tool

BOYUEJIA Sandwich Wall Panels Installation?Guide

Sandwich Wall Panel Installation Diagram

eps sandwich panels installation 1

Connection between Sandwich Wall Panel and Wall

eps sandwich panels installation 2

Connection between Sandwich Wall Panel and Window & Door

eps sandwich panels installation 3

Line Pipe Install Vertical View

eps sandwich panels installation 4

Hanging Nail Installation

eps sandwich panels installation 5

Bathroom Waterproof Solution

eps sandwich panels installation 6

Sandwich Wall Panels Installation Guide Videos